I. stage
Reconstruction of the Spiš castle, the Romanesque palace and the western palaces – engineering networks, stage I completed implementation (2018 – 2020).
II. stage
Reconstruction of Spiš Castle, Romanesque Palace and Western Palaces, II. stage of ongoing implementation (2021 – 2024).
III. stage
Reconstruction of Spiš Castle, III. stage
Completed pre-project preparation (2022).
Project preparation (2023 – 2024).
Planned implementation of reconstruction (2024 – 2027).
IV. stage
Reconstruction of Spiš Castle, IV. stage
Planned pre-project and project preparation (2024-2025).
Planned implementation of reconstruction (2025 – 2028).
V. stage
Reconstruction of Spiš Castle, V. stage
Planned pre-project and project preparation (2024-2025).
Planned implementation of reconstruction (2025 – 2027).
We are reconstructing and saving Spiš Castle for you and future generations.